WHY IS IT SCHEDULING FOR TWO DAYS WHEN WE ONLY PUT ONE DAY



 
 
Thread Tools Display Modes
  #1  
Old October 3rd, 2005, 07:48 PM
Tara
external usenet poster
 
Posts: n/a
Default WHY IS IT SCHEDULING FOR TWO DAYS WHEN WE ONLY PUT ONE DAY

when we put an event down for one day, it is showing as two days whenever our
calendar is viewed by a shared user...the date and time are correct when we
punch them in, but when shared it shows as being different? Any ideas?
  #2  
Old October 3rd, 2005, 08:10 PM
Vince Averello [MVP-Outlook]
external usenet poster
 
Posts: n/a
Default

Are all users set to the same time zone? If not, you'll see what you're
seeing

"Tara" wrote in message
news
when we put an event down for one day, it is showing as two days whenever
our
calendar is viewed by a shared user...the date and time are correct when
we
punch them in, but when shared it shows as being different? Any ideas?



  #3  
Old October 4th, 2005, 06:54 AM
MaryO
external usenet poster
 
Posts: n/a
Default

Check that either your calendar or the calendar you are sending to is on the
correct time zone (Tools Menu/Calendar Options/Time Zone). This is quite
separate from the regional settings in your Control panel.

"Tara" wrote:

when we put an event down for one day, it is showing as two days whenever our
calendar is viewed by a shared user...the date and time are correct when we
punch them in, but when shared it shows as being different? Any ideas?

  #4  
Old October 8th, 2005, 01:00 AM
Weinie
external usenet poster
 
Posts: n/a
Default

Just fixed this problem, but while the correct time zone was chosen in
Outlook, the "Adjust for Daylight Savings Time" box was not checked on some
of the workstations. This put that user an hour ahead (while we are on DST)
or the rest, and make their calendar entries move to a 2 day event.
--
Joe


"MaryO" wrote:

Check that either your calendar or the calendar you are sending to is on the
correct time zone (Tools Menu/Calendar Options/Time Zone). This is quite
separate from the regional settings in your Control panel.

"Tara" wrote:

when we put an event down for one day, it is showing as two days whenever our
calendar is viewed by a shared user...the date and time are correct when we
punch them in, but when shared it shows as being different? Any ideas?

 




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is Off
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Scheduling vacation days laura.klenotic \(removethis\) @antaressolutions.co Calendar 2 September 10th, 2006 11:47 PM
Days, Weeks, And Months Aron Running & Setting Up Queries 2 September 18th, 2005 11:48 PM
switch statement to calculate field Nancy Using Forms 12 May 18th, 2005 04:08 AM
What is wrong w/ this query? Tom Ellison Running & Setting Up Queries 3 November 19th, 2004 12:30 AM
Counting Consecutive Days Mel Worksheet Functions 1 April 28th, 2004 11:13 PM


All times are GMT +1. The time now is 08:50 AM.


Powered by vBulletin® Version 3.6.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 OfficeFrustration.
The comments are property of their posters.