A Microsoft Office (Excel, Word) forum. OfficeFrustration

If this is your first visit, be sure to check out the FAQ by clicking the link above. You may have to register before you can post: click the register link above to proceed. To start viewing messages, select the forum that you want to visit from the selection below.

Go Back   Home » OfficeFrustration forum » Microsoft Access » Setting Up & Running Reports
Site Map Home Register Authors List Search Today's Posts Mark Forums Read  

how to show data in report as a Gantt Chart?



 
 
Thread Tools Display Modes
  #1  
Old May 1st, 2009, 10:59 AM posted to microsoft.public.access.reports
Haroon
external usenet poster
 
Posts: 30
Default how to show data in report as a Gantt Chart?

hi

i want to show data on report as a gantt chart view? is there a way of doing
this?

i have start date, finish date, project name/id, task name etc.


thanks.
  #2  
Old May 1st, 2009, 02:41 PM posted to microsoft.public.access.reports
Rob Parker[_3_]
external usenet poster
 
Posts: 173
Default how to show data in report as a Gantt Chart?

Hi Haroon,

I notice that this is a repost of a previous question, and that the flexgrid
solution suggested was not suitable for you.

I don't have a quick answer, but a comment. The chart object used in Access
is essentially the same as the chart object used in Excel. Neither of these
offer a Gantt chart as a built-in alternative. I've never tried producing a
Gantt chart in Access, but I have done so in Excel (many years ago). It
took a lot of trickery to get it to work, but it could be done. And so, if
you can come up with a very fancy query as the RowSource for your chart, and
format the chart appropriately - and that may take some coding effort, if
the number of fields in the RowSource varies, as it's likely to do for a
dynamic project with changing numbers of tasks - then it is conceivably
possible. If you want to try it, Google for Gantt chart in Excel to find
how to do it there, and use that as a start point.

Sorry I can't help more,

Rob

PS. A google search using "gantt chart access" (as individual words, not a
quoted string) gives some possible solutions on the first page of results.
I haven't tried any of these.


Haroon wrote:
hi

i want to show data on report as a gantt chart view? is there a way
of doing this?

i have start date, finish date, project name/id, task name etc.


thanks.



  #3  
Old May 1st, 2009, 03:24 PM posted to microsoft.public.access.reports
Duane Hookom
external usenet poster
 
Posts: 7,177
Default how to show data in report as a Gantt Chart?

There is a sample at http://www.access.hookom.net/Samples.htm in the Calendar
Reports download.

--
Duane Hookom
Microsoft Access MVP


"Haroon" wrote:

hi

i want to show data on report as a gantt chart view? is there a way of doing
this?

i have start date, finish date, project name/id, task name etc.


thanks.

 




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is Off
HTML code is Off
Forum Jump


All times are GMT +1. The time now is 02:25 PM.


Powered by vBulletin® Version 3.6.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 OfficeFrustration.
The comments are property of their posters.